FDA's recall database dates the start of one Class I recall to 6 May 2026. Version 5.10.2 of the software for Fresenius Kabi's Ivenix large-volume pump had been released as the remedy for an earlier Class I software recall, begun on 14 November 2025. The new version could show a false battery-health value, "typically 69%", and the pump could then shut itself down for a depleted battery unless it was running on AC power. The remedy for one software recall had become the subject of the next. Part IX sets out, as of October 2026, the standards a pump is built and tested to, how the United States, the European Union and India decide whether it may be sold, and how problems are found and corrected once pumps are in use, mapping the mechanisms of the earlier parts onto the rules.

27 — Standards

The standards that define a pump.

+ The questionWhich standards set what a pump must do and how it is tested?

Product standards and process standards

A standard, in the sense this part uses, is a document published by a standards body, such as the International Electrotechnical Commission (IEC) or the International Organization for Standardization (ISO), that states what a product or a process must achieve and, usually, how to show it. A standard binds no one by itself. It gains force when a regulator gives it standing: FDA recognizes standards, the European Union lists them as harmonized, and India's Medical Devices Rules make an Indian standard mandatory where one exists (Chapters 28 to 30). A maker of Chapter 26 that sells in more than one of these markets finds most of what each regulator asks of a pump written in the same few documents, adopted in different ways.

Two kinds of standard matter for a pump. Product standards say what the pump must do and how a test laboratory checks it: the IEC 60601 family for medical electrical equipment, the ISO 80369 family for the connectors on its sets, and ISO 28620 for pumps with no electrical drive. Process standards say how the maker must work: ISO 14971 for risk management, IEC 62366-1 for usability engineering and IEC 62304 for the software life cycle. A product standard can be checked on a finished pump. A process standard is checked in the maker's files, which is where FDA's 2010 white paper on infusion pumps placed many of the problems it listed, in "deficiencies in device design and engineering."

Within the 60601 family the structure is layered. A general standard, IEC 60601-1, covers every medical electrical device. Collateral standards, numbered 60601-1-x, each add requirements on one topic, such as alarms, for all such devices. A particular standard, numbered 60601-2-x, amends and adds to the general standard for a single type of device, and for infusion pumps that is IEC 60601-2-24. A pump is therefore tested to a stack: the general standard as its particular standard modifies it, plus every collateral standard that applies, while the process standards run underneath all of them.

70 — The standards stack for an infusion pump
PRODUCT STANDARDS · WHAT THE PUMP MUST DO IEC 60601-2-24 · PARTICULAR STANDARD INFUSION PUMPS AND CONTROLLERS 2012, second edition · accuracy, bolus, occlusion, by weighing 60601-1-2 EMC 2014 + 2020 60601-1-8 ALARMS 2006 + 2012 + 2020 60601-1-11 HOME USE 2015 + 2020 IEC 60601-1 · GENERAL STANDARD 2005, amended 2012 and 2020 · every medical electrical device ISO 80369-1, -7, -3 CONNECTORS 2025 · 2021 · 2016 + 2019 AAMI TIR101 US FLUID-DELIVERY TESTING 2021, reaffirmed 2026 recognized by FDA same purpose, different method ISO 28620 NO ELECTRICAL DRIVE 2020 · outside the 60601 family PROCESS STANDARDS · HOW THE MAKER WORKS ISO 14971 · RISK MANAGEMENT 2019 IEC 62366-1 · USABILITY 2015 + 2020 IEC 62304 · SOFTWARE LIFE CYCLE 2006 + 2015 AMENDS THE GENERAL STANDARD FOR PUMPS Shaded: the 60601 family. Editions in force, October 2026. IEC and ISO catalogs; ANSI catalog for TIR101.
ReadoutFocal detail
Plate 70 — A pump is tested to the general standard as the particular standard amends it, plus the collateral standards that apply; the process standards for risk, usability and software sit under all of them.

The general standard and its collaterals

IEC 60601-1 is in its third edition, published in 2005 and amended in 2012 and 2020; the consolidated text of August 2020, numbered edition 3.2, runs to 842 pages. A working document of IEC's medical-equipment committee listed an edition 4 as in development in July 2026, without a stage or a date. Three collateral standards bear most on a pump. IEC 60601-1-2, on electromagnetic compatibility, is the 2014 edition amended in 2020; it concerns whether the pump keeps working beside other equipment's emissions without disturbing them. IEC 60601-1-8, on alarm systems, dates from 2006 with amendments in 2012 and 2020, and defines alarm priorities by degree of urgency (Chapter 15). IEC 60601-1-11, of 2015 amended in 2020, covers equipment used in the home.

A standard's year marks when its edition first appeared

IEC 60601-1:2005 is the current general standard as amended in 2020, IEC 62304:2006 is the current software standard as amended in 2015, and ISO 80369-7:2021 was confirmed as current on 28 September 2026. The year in a standard's name says when that edition was first published. Whether it is in force, amended, confirmed at review or replaced is recorded in the standards body's catalog, and a test report should name the edition and every amendment it applied.

What IEC 60601-2-24 asks of a pump

IEC 60601-2-24 is the particular standard for infusion pumps and controllers. Its second edition, published on 19 October 2012, replaced the first of 1998, aligned the text with the 2005 general standard as amended in 2012, renumbered its clauses and added requirements on usability and alarms. Its scope covers infusion pumps, including enteral nutrition pumps, ambulatory pumps and syringe or container pumps, and volumetric infusion controllers, which regulate a flow driven by gravity rather than pump it. It reaches the administration set only where the set's characteristics affect the pump's safety or performance. Pumps without an electrical drive are left to ISO 28620, and implanted pumps are excluded.

A commercial test laboratory describes the core tests as weighing, by the gravimetric method of Chapter 9. Bolus volumes are weighed the same way, and occlusion is tested on a closed line, recording the pressure at which the pump alarms and the mass it releases once the line opens, the unintended bolus of Chapter 12. A certifier's presentation on the 2012 edition gives the test rates set out in Chapter 9, and says that the instructions must state the range of rates and the conditions, such as temperature, under which the stated accuracy holds. The standard fixes how accuracy is measured (Chapter 9), and the maker declares what the pump achieves, so a test is judged against the accuracy the pump's own instructions state.

Solved example: judging one test hour against a stated accuracy

A volumetric pump runs at 25 mL/h with the balance read every 30 seconds, so each reading should add 25 ÷ 120 = 0.208 mL, about 208 mg of water. Over the analyzed hour the balance gains 24.10 g, an illustrative reading rather than a published result. Taking the water at 20 °C, where it weighs 0.99821 g per mL, the volume is 24.10 ÷ 0.99821 = 24.14 mL, and the error is (24.14 − 25) ÷ 25 = −3.4 %. Against ±5 %, the figure BD states for its Alaris Pump Module and Fresenius Kabi for its Ivenix pump at this rate, the pump passes. Against the ±3 % that ICU Medical states for the Plum Solo under TIR101's standard conditions, the same −3.4 % would fail. TIR101, however, reads the balance every 10 seconds under its own conditions, so a result from this test and a TIR101 result are not interchangeable. The same hour of data passes or fails according to the claim it is judged against.

A particular standard due for revision

The 2012 edition's stability date, the year until which IEC expected to leave it unchanged, is 2026. According to national standards bodies' copies of IEC's project records, a first project for a third edition was deleted on 31 October 2024. A second project reached a committee draft, the first text circulated for comment, and its comment period closed on 21 August 2026. A draft for vote and a final draft follow, and no publication date is forecast. The British Standards Institution's comment draft names subcutaneous, body-worn and syringe pumps in its scope; whether the test method will change is not known. As of October 2026 the 2012 edition is current, and India adopted it unchanged as IS 13450 (Part 2/Sec 24):2019.

71 — Editions of the pump standards, 1998 to 2028
OCTOBER 2026 1998 2002 2006 2010 2014 2018 2022 2026 IEC 60601-2-24 ED 1 · 1998 ED 2 · 2012 IEC 60601-1 ED 3 · 2005 ED 4 IN DEVELOPMENT IEC 60601-1-8 IEC 62304 ED 1 · 2006 ED 2 EXPECTED 2026 TO 2027 IEC 62366-1 ISO 14971 ED 3 · 2019 ISO 28620 ED 2 · 2020 ISO 80369-1 ED 2 · 2018 ED 3 · 2025 ISO 80369-7 ED 2 · 2021 AAMI TIR101 REAFFIRMED ED 3 PROJECT DELETED NO DATE CD COMMENTS CLOSED THIRD EDITION AT COMMITTEE DRAFT edition amendment confirmed or reaffirmed not published IEC and ISO catalogs; national-body copies of IEC project records; ANSI catalog for TIR101; IEC 62304 second edition timing from a vendor report (12 Jun 2026).
ReadoutFocal detail
Plate 71 — The editions in force in October 2026 first appeared between 2005 and 2025, and most have been amended or confirmed since; the third edition of the pump standard and the second of the software standard are still drafts.

Connectors, non-electric pumps and the US test report

ISO 80369 covers the small-bore connectors that join a set to a syringe, a catheter or a feeding tube, so that connectors meant for different routes cannot be joined by mistake; Chapter 19 gives the editions of its parts for general requirements (part 1), the Luer (part 7) and enteral connectors (part 3). ISO 28620, for portable pumps with no electrical drive, such as the elastomeric pumps of Chapter 7, is a second edition of 2020, confirmed in August 2026.

In the United States, fluid-delivery testing has a document of its own, AAMI TIR101:2021, reaffirmed in 2026, whose method Chapter 9 sets beside the particular standard's. FDA recognizes TIR101 and not IEC 60601-2-24 (Chapter 28). ICU Medical's 2025 summary for the Plum Solo states accuracy against TIR101 and does not cite the particular standard, while DEKA's 2026 summary for the RemunityPRO+ cites IEC 60601-2-24.

Risk, usability and software processes

ISO 14971, the risk management standard, is the third edition of 2019, confirmed in March 2025 with no revision under way. It asks the maker to identify hazards, estimate and control their risks, and judge the risk that remains, across the product's life. The product standards feed its file, from an occlusion alarm limit to an alarm priority to a use error seen in testing. IEC 62366-1, published in 2015 and amended in 2020, is the usability engineering process of Chapter 18. IEC 62304, the software life-cycle process of Chapter 20, is still the 2006 edition with its 2015 amendment.

The second edition of IEC 62304 is not published as of October 2026. Its design specification widens the scope from medical device software to health software and replaces the three software safety classes with two levels of process rigor: class A becomes level I, and classes B and C become level II. A software vendor, a secondary source, reported in June 2026 that the draft had reached the final-draft stage in May, with publication expected late in 2026 or in 2027. An earlier attempt at a second edition was abandoned.

StandardEdition in force, October 2026What it asks of a pumpChapter
IEC 60601-12005, amended 2012 and 2020; edition 4 in developmentgeneral safety and performance of electrical equipment—
IEC 60601-1-82006, amended 2012 and 2020alarm systems and their priorities15
IEC 60601-2-242012 (second edition); third at committee draftaccuracy, bolus and occlusion tests, by weighing8, 9, 12
ISO 80369-1, -7, -32025; 2021; 2016 amended 2019connectors that resist misconnection19
ISO 286202020 (second edition)pumps with no electrical drive7
ISO 149712019risk management over the life cycle—
IEC 62366-12015, amended 2020usability engineering process18
IEC 623042006, amended 2015; second edition unpublishedsoftware life-cycle process20
AAMI TIR1012021, reaffirmed 2026fluid-delivery performance testing in the US9
Write the edition into every test plan

Name each standard in a test plan with its edition and amendments, as IEC 60601-1:2005+A1:2012+A2:2020 rather than IEC 60601-1, and check the ISO and IEC catalogs for confirmations and replacements before each submission. An Indian maker testing a pump for CDSCO can cite IS 13450 (Part 2/Sec 24):2019, identical to IEC 60601-2-24:2012, and should add AAMI TIR101 if the same pump is meant for the United States. Follow the third edition of IEC 60601-2-24 and the second of IEC 62304 through their drafts, because a pump designed in 2026 may reach a regulator after both are published.

+ What this chapter established
  • A standard binds only through a regulator; product standards say what a pump must do and how it is tested, and process standards say how its maker must work.
  • IEC 60601-2-24:2012, the particular standard for pumps, tests accuracy, bolus and occlusion at fixed rates by weighing what the pump delivers, judged against the accuracy the maker declares, and its third edition is at committee draft.
  • The editions in force in October 2026 include ISO 80369-1:2025, ISO 80369-7:2021, ISO 28620:2020, ISO 14971:2019, IEC 62366-1 as amended in 2020 and IEC 62304 as amended in 2015.
  • In the United States, fluid-delivery testing follows AAMI TIR101:2021, reaffirmed in 2026, which FDA recognizes while it does not recognize IEC 60601-2-24.