09 — The operator as a barrier

A person in the loop.

+ The questionWhen can someone answering an alarm count as protection, and why so rarely above SIL 1?

The alarms read the gauge that had stuck

In Buncefield's control room the gauge reading for Tank 912 showed no change for nearly three hours. The gauge's three level alarms all worked from that reading. A supervisor could set a "user high" to call for intervention, a high level sat below the tank's maximum working level, and a high-high level sat below the level at which the independent switch was meant to act. The supervisors used these alarms to run the fill rather than to guard it. The Competent Authority reported in 2011 that each of the eight supervisors used the alarm levels in their own way, and that the level sometimes passed the high alarm, less often rose to the high-high, and on occasions went beyond it.

An alarm is a layer of protection in Chapter 7's sense only with everything needed to prevent the hazardous event: a sensor, an annunciator that turns the sensor's signal into an alarm signal, a person who responds, and a final element that the person can drive, such as a valve on the incoming line. The four work as one loop, and each must be apart from the other layers and from the cause of the demand, as PSLG requires in its 2009 guidance for fuel storage sites. An alarm generated by a tank gauge cannot be relied on where the demand comes from a failure of that gauge. At Buncefield the failure of the gauge created the demand, so alarms set on the gauge's reading could not answer it (Chapter 7). Chapter 11 shows why the independent switch could not act.

Four steps against the clock

Between the alarm signal and the safe state, the person responding observes, diagnoses, plans and acts: the four steps that PSLG's guidance names. Each takes time, and the process goes on while they happen. The time that counts is the window from the moment the alarm sounds to the point of no return, after which no action can prevent the hazardous event. All four steps, with the travel of the final element, must fit inside that window. The window is shorter than the process safety time of Chapter 4, which starts at the failure itself, because the alarm sounds only once the deviation has reached its set point.

Observation is quick when the alarm is distinct, and it depends on what the person can see. At Buncefield one screen served a number of tanks and showed only one in full at a time, and on the night Tank 912's display sat at or near the back of a stack of four others. Diagnosis and planning are the slow steps. Problems that develop over time, with uncertain information, are particularly hard to detect, and operators may occasionally hesitate where a shutdown might lead to later criticism. Action needs a final element within reach. At Buncefield the supervisors controlled one of the three incoming pipelines, and the other two could be stopped only by a telephone call to another terminal, an independent high-level switch, or a manual call point on the adjacent site.

Under PSLG's guidance the time a response needs is judged case by case, and Chapter 22 sets a tank's alarm levels from such times. A walk-through of the task gives the minimum response time, to which the guidance adds delays from uncertainty, hesitation and communication. Two consultancies give working rules. In a 2017 conference paper, Bridges, president of the Process Improvement Institute, aims for a maximum allowable response time of half the process safety time or less. His firm's method credits a response only where more than 10 minutes are allowed for trouble-shooting in the field, or more than 5 from the control room alone. A 2009 white paper from exida, a certification and consulting company, reports one operating company's rule: no response can be claimed as a layer where the process safety time is under 10 minutes. The white paper counts the process safety time to the hazardous event itself.

18 — The operator's time budget
Schematic, not to scale: one response, from the alarm to the point of no return. OBSERVE DIAGNOSE PLAN ACT FINAL ELEMENT MOVES ALLOWANCE FOR UNCERTAINTY, HESITATION, COMMUNICATION MARGIN INITIATING EVENT ALARM SOUNDS POINT OF NO RETURN everything must end before this point HAZARDOUS EVENT WALK-THROUGH TIME (THE MINIMUM) TIME AVAILABLE TO THE OPERATOR PROCESS SAFETY TIME One consultancy's rule, in its own sense of the process safety time: a maximum allowable response time of half of it.
Basic controlDangerous failureOperator and alarmFocal detail
Plate 18 — The operator's four steps, the final element's movement and an allowance for delay must all fit between the alarm and the point of no return, a window shorter than the process safety time.

Alarms used for control, or lost in a flood

The Competent Authority called the practice in Buncefield's control room working to alarms. Used to end a fill, the alarm and the supervisor become part of the basic control of the process, the control the alarm was meant to guard, so a lapse in either starts an overfill instead of stopping one. The same alarm cannot then also be the layer that answers the overfill. Filling should instead stop before the high alarm sounds, so that level alarms do not routinely sound, as PSLG's guidance says.

The other way to lose an alarm is among other alarms. At the Texaco refinery at Milford Haven on 24 July 1994, two operators had 275 alarms to handle in the last 11 minutes before the explosion. The Health and Safety Executive, the UK regulator, found that the excessive number of alarms reduced the effectiveness of their response. In an information sheet on alarm handling issued in 2000, HSE gives as good practice a long-term average of no more than one alarm every 10 minutes in normal operation, and no more than 10 displayed in the first 10 minutes after a major upset. HSE's toolkit for its inspectors calls 20 to 100 alarms in 10 minutes hard to cope with.

A burst of that kind is an alarm flood: more than 10 new alarms in 10 minutes. Two control-system makers give that definition from the alarm-management guides EEMUA 191 and ISA-18.2. Siemens gave it in 2014, describing the 2009 edition of ISA-18.2, and Emerson in 2016. The guides now stand at EEMUA 191's revised fourth edition of 2024 and at ISA-18.2-2016, whose international counterpart is IEC 62682:2022. An alarm earns credit in PSLG's guidance only where the operator can pick it out among potentially many others. In a 2016 article, Fialkowski and colleagues go further: with a high time in flood, "it may not be appropriate to take any risk reduction for the response to any alarm". Two of the three authors worked for Siemens and one for DuPont.

19 — An alarm rate over a shift
0 5 10 15 20 25 30 NEW ALARMS IN EACH 10 MINUTES 1 IN 10 min: NORMAL-OPERATION TARGET 10 IN 10 min: UPSET MAXIMUM 20 TO 100 IN 10 min: HARD TO COPE WITH 0 1 2 3 4 5 6 7 8 9 10 11 12 HOURS INTO A 12-HOUR SHIFT ALARM FLOOD: MORE THAN 10 NEW ALARMS IN 10 MINUTES ENDS: FEWER THAN 5 MILFORD HAVEN, 24 JULY 1994: 275 ALARMS IN 11 MINUTES, TWO OPERATORS the flood begins: the one alarm that matters is among the rest Schematic shift, not a record. Targets: HSE, Better alarm handling (2000) and inspectors' toolkit. Flood: Siemens (2014) and Emerson (2016), from EEMUA 191 and ISA-18.2.
Dangerous failureOperator and alarmFocal detail
Plate 19 — Over most of an illustrative 12-hour shift the alarm rate stays below HSE's target of one alarm every 10 minutes. In an upset it passes 10 in 10 minutes, the start of a flood, and the one alarm that calls for protection must be found among the rest. At Milford Haven two operators had 275 alarms in 11 minutes.

The chance of failure turns on time

The probability that a person fails to respond correctly is a human error probability. Three methods recur, and each starts from a nominal probability for a kind of task and multiplies it by factors for its conditions. THERP, the oldest, was written by Swain and Guttmann for the US Nuclear Regulatory Commission in 1983. HEART, which Williams published from 1985, sorts tasks into nine generic types, each with its own nominal probability: 0.55 for a totally unfamiliar task done at speed, for example, and 0.003 for restoring a system by procedure with some checking. Bell, of HSE's laboratory, reviewed the published evidence for HEART's multipliers in 2016 with Williams, who devised the method. They kept 180 of about 25,000 papers and found that time pressure makes an error about 11 times more likely.

SPAR-H makes the weight of time explicit. Gertman and colleagues at the Idaho National Laboratory wrote it in 2005 for the same commission. SPAR-H was built for the crews of US nuclear power plants responding to initiating events, and its numbers come from that setting. The method starts a diagnosis at 0.01 and an action at 0.001 and multiplies each by performance shaping factors, conditions such as the time available and stress. With inadequate time the failure is certain. Barely adequate time for a diagnosis, about two-thirds of the time it normally needs, multiplies the probability by 10, and extra or expansive time divides it by 10 or 100. High stress doubles the probability that a diagnosis fails.

20 — The chance a diagnosis fails, by time available
CHANCE THE DIAGNOSIS FAILS 1 1 in 10 1 in 100 1 in 1,000 1 in 10,000 0.1: THE CREDIT LIMIT FOR AN ALARM AND OPERATOR INADEQUATE BARELY ADEQUATE ABOUT TWO-THIRDS OF NOMINAL NOMINAL EXTRA 1 TO 2 TIMES NOMINAL EXPANSIVE OVER 2 TIMES NOMINAL CERTAIN 1 IN 10 1 IN 100 1 IN 1,000 1 IN 10,000 barely enough time: the diagnosis alone takes the whole credit SPAR-H (US NRC, 2005), at-power worksheet: nominal diagnosis 0.01 times the time factor alone; built for nuclear plant crews. Credit limit: HSE, PSLG.
Operator and alarmFocal detail
Plate 20 — In SPAR-H's nuclear worksheet, barely adequate time raises the chance that a diagnosis fails tenfold, to 1 in 10, the whole credit an alarm and operator may claim.
Solved example: one response, three amounts of time

A response here is one diagnosis and one action, at SPAR-H's nominal 0.01 and 0.001. With barely adequate time, the diagnosis becomes 0.01 × 10 = 0.1, and an action given only about the time it needs becomes 0.001 × 10 = 0.01. The response fails if either step fails, so the two add to about 0.11. Extra time for the diagnosis means more than 30 minutes and up to twice the time it needs. With that, and five times the time the action needs, the two steps fall to 0.001 and 0.0001, about 0.0011 together, or 1 in 900. Time alone moves the result about 100-fold. High stress, applied here to the diagnosis alone, doubles the worst case's diagnosis to 0.2. The response then fails at about 0.21, or 1 in 5, about 190 times the best case. With nominal time and no stress the two steps stay at 0.01 and 0.001, about 1 in 90 together. That falls short of the 1 in 100 that a SIL 2 function must beat (Chapter 8). Each case has fewer than three unfavorable factors, so the method multiplies them directly. The values come from a nuclear method and show how much time weighs, not what any real control room achieves.

The layer fails more often than any one of its steps

A probability for one task, such as 0.001 for an action, is easily carried into an analysis as the probability that the whole operator layer fails. The layer holds the diagnosis and the planning as well as the action, and the sensor, the annunciator and the final element besides. A 2009 review by HSE's laboratory examined the overfill studies of seven companies (Chapter 7). It judged unjustified the human error probabilities that the studies took from a table in Part 3 of IEC 61511. In PSLG's summary of that review, probabilities set too low come first among the failings of early studies.

The credit stops at a factor of ten

The steps already traced show why an operator's response earns only limited credit. A SIL 2 function must fail fewer than once in 100 demands, and the solved example reaches that only with ample time and no stress. A demand is also an abnormal event, and PSLG's guidance notes that on a well-run site an operator may never have met one, so that without training or drills the right response may be unfamiliar.

Regulators draw the boundary at a factor of 10. In guidance to its specialist inspectors, HSE states that the 2017 British edition of IEC 61511 "does allow an operator as part of a SIS", a safety instrumented system. That guidance, updated in 2020, sorts alarm functions that include an operator's response by the risk reduction they claim. Up to a factor of 10, a probability of failure on demand of 0.1 or more, the function is a low-integrity safety instrumented alarm function. Beyond 10 it is a safety instrumented alarm function. Singapore's regulator of major hazard installations draws the same line at 10 for the basic control system.

The same boundary appears from the alarm's side in PSLG's guidance. An alarm system outside IEC 61511 may be credited an overall probability of failure on demand no lower than 0.1, even where one of its components is credited lower, and under time pressure a higher probability may be considered. A claim below 0.1 makes the alarm system a safety instrumented function, or SIF, to be assessed to SIL 1, with its human part assessed step by step. Above SIL 1 the guidance allows no claim: "SIL 2 or higher cannot be claimed for a SIF that includes operator response". PSLG takes that rule from the 2007 edition of EEMUA 191. The guidance accepts a site without automatic overfill protection only if an automatic system would create more serious risks elsewhere, and for such a site its wording is softer: "It is unlikely that an operator can be included in an overfill prevention system rated above SIL 1".

The exida white paper goes beyond the regulators' line, grading a drilled response at 0.01 and calling such a response rarely achieved in most process plants. Bridges caps the credit for any human response at 0.1, the regulators' own figure. Fialkowski and colleagues give a well-designed safety alarm with its own operator interface a potential factor of 100.

Whether a person may sit inside a SIL 1 function at all was argued at a symposium in 2012. The UK petroleum industry had built a gap analysis tool to assess an operator as part of a SIL 1 overfill function. Embrey and Henderson, consultants in human reliability, reviewed the tool in a study commissioned for the industry's association. They found that the tool gave no explicit link from its scores to a probability of failure on demand: "A major problem is the lack of available, reliable data in this area." At the same symposium Derbyshire, a consultant from DNV, argued that under the 2004 edition of IEC 61511 an operator must not be considered part of a safety instrumented function and cannot act as its logic solver. HSE's guidance of 2020 reads the 2017 edition the other way.

At the cot side the cutout acts without a person

The incubator of Chapter 4 puts both kinds of response side by side. When the air or skin temperature leaves its band, the controller raises an alarm condition, and the alarm signal at the cot side asks a nurse to find the cause. The independent channel's cutout opens the heater circuit on its own sensor's reading and asks no one.

The alarm standard for medical electrical equipment, IEC 60601-1-8, assigns each alarm a priority through risk analysis. A high priority calls for an immediate response, which the standard's rationale ties to injury within seconds to several minutes. A medium priority calls for a prompt response, for problems that cause no injury until several to many minutes have passed. A compliance firm's 2015 cross-reference of the alarm standards gives these priorities, and it gives the rationale's minutes in the firm's own paraphrase. The edition in force is the 2006 text with amendments of 2012 and 2020.

Whatever minutes the alarm's priority allows a nurse, the incubator's protection does not depend on them. The alarm brings a person to find the cause and restore care, while the cutout needs no one at the cot side, so the protection holds whoever hears the alarm and however long they take. PSLG's guidance prefers automatic overfill protection, and the Competent Authority drew the same lesson from the Baker report on the Texas City refinery explosion: "process safety protection systems should not rely on operator response to alarms". Chapter 15 of the infusion-pump guide, Every drop accounted for, treats the alarms a person at the bedside acts on.

Credit a person only for a response that can be shown

Where a person is part of a layer, write into the safety requirements specification the alarm, its set point, the expected response, the time to the point of no return, and a walked-through response time with an allowance for delay (Chapter 17). Give the alarm its own sensor and the person a final element within reach, both apart from the cause of the demand and from the other layers. Credit no more than a factor of 10 unless the function is engineered and assessed to SIL 1, and claim nothing above SIL 1. Keep the alarm out of routine control, measure alarm rates against HSE's benchmarks, and drill the response. In a device, let an automatic channel carry the protection.

+ What this chapter established
  • An alarm and the person who answers it count as a layer only as a complete loop of sensor, annunciator, person and final element, each apart from the cause of the demand, and Buncefield's alarms read the gauge whose failure created the demand.
  • The four steps of a response must fit between the alarm and the point of no return, and in SPAR-H's nuclear values the time available alone moves the chance that a response fails about a hundredfold.
  • An alarm used for routine control becomes part of the control it was meant to guard, and in PSLG's guidance an alarm earns credit only where the operator can pick it out among potentially many others. HSE's good practice is a long-term average of no more than one alarm every 10 minutes in normal operation.
  • HSE's guidance and PSLG credit an alarm and a person's response with at most a factor of 10 outside a SIL 1 function, and PSLG allows no claim of SIL 2 or higher for a function that includes operator response.
Created with Claude (Anthropic).